For a certain loading condition, a saturated clay layer undergoes 40% consolidation in a period of 178 days. What would be the additional time required for further 20% consolidation to occur? |
| A. | 89 days |
| B. | 222.5 days |
| C. | 267 days |
| D. | 400.5 days |
| Answer» C. 267 days | |