| 1. |
Eight persons can finish a work in 20 days. After 5 days they were requested to complete the work in the next 8 days. How many more persons should join the group to fulfill the requirement? |
| A. | 12 |
| B. | 15 |
| C. | 23 |
| D. | 7 |
| Answer» E. | |