During the main program stage, like schedule conflicts, another frequent placing conflict is |
| A. | Decision making Conflicts |
| B. | Technical Conflicts |
| C. | Functional conflicts |
| D. | Personnel's conflicts |
| Answer» C. Functional conflicts | |