Critical path lies along the activities having tot...
1.
Critical path lies along the activities having total float
A.
positive
B.
negative
C.
zero
D.
same.
Answer» D. same.
Show Answer
Discussion
No Comment Found
Post Comment
Related MCQs
If is the latest allowable event occurrence time, total activity slack(s), is equal to
In the given figure, the network of a project represents
In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace?
The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as
For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is
In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having
Consider the following activities in a building construction: 1. Concreting of roofslabs 2. Brick-jelly lime concrete terracing 3. Erection of form work forslab 4. Construction of parapet wall in terrace
Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is
Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth ofcut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimumdepth, (iv) Output can be increased by increasing the size of shovel. Of these statements
If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good