MCQOPTIONS
Saved Bookmarks
| 1. |
Considering dual rate method, if employees work for 8500 budgeted hours at $120 per hour and work for 9500 actual hours at $110 per hour, then total cost would be |
| A. | 2,078,000 |
| B. | 3,078,000 |
| C. | 2,065,000 |
| D. | 3,065,000 |
| Answer» D. 3,065,000 | |