1.

Consider a project with the following functional units:Number of user inputs = 50Number of user outputs = 40Number of user inquiries = 35Number of user files = 06Number of external interfaces = 04Assuming all complexity adjustment factors  and  weighing  factors  as average, the function points for the project will be

A. 135
B. 722
C. 675
D. 672
Answer» E.