| 1. |
Calendar Ratio = |
| A. | Number of actual working days in a period x 100 Number of working days in the budget period |
| B. | Actual hours worked x 100 Budgeted hours |
| C. | Standard hours for actual production x 100 Actual hours worked |
| D. | Standard hours for actual productionx 100 Budgeted standard hours |
| Answer» B. Actual hours worked x 100 Budgeted hours | |