| 1. |
Calculate the quantity of earthwork for 200 m length for a portion of road in an uniform ground the heights of banks at the two ends being 1.00 m and 1.60 m. The formation width is 10 mm and side slope 2:1. Assume that there is no traverse slope. |
| A. | 3276 cu m |
| B. | 5676 cu m |
| C. | 6757 cu m |
| D. | 1121 cu m |
| Answer» B. 5676 cu m | |