At the completion of the forward and backward passes, the slack for an activity is given by the |
| A. | difference between early start and early finish |
| B. | difference between early start and latest finish |
| C. | difference between latest start and early finish |
| D. | amount of idle labor on the critical path |
| Answer» B. difference between early start and latest finish | |