Assume the following regarding the development of a software system P:- Estimated lines of code of P: 33, 480 LOC- Average productivity for P: 620 LOC per person-month- Number of software developers: 6- Average salary of a software developer: Rs. 50,000 per monthIf E, D and C are the estimated development effort (in person-months), estimated development time (in months), and estimated development cost (in Rs Lac) respectively, then (E, D, C) = ...............

A. (48, 8, 24)
B. (54, 9, 27)
C. (60, 10, 30)
D. (42, 7, 21)
Answer» C. (60, 10, 30)