MCQOPTIONS
Saved Bookmarks
| 1. |
Assume that the software team defines a project risk with 80% probability of occurrence of risk in the following manner:Only 70 percent of the software components scheduled for reuse will be integrated into the application arid the remaining functionality will have to be custom developed: If 60 reusable components were planned with average component size as ' 100 LOC and software engineering cost for each LOC as $ 14, then the risk exposure would be |
| A. | $ 25,200 |
| B. | $ 20,160 |
| C. | $ 17,640 |
| D. | $ 15,120 |
| Answer» E. | |