Assume that the software team defines a project risk with 80% probability of occurrence of risk in the following manner:Only 70 percent of the software components scheduled for reuse will be integrated into the application arid the remaining functionality will have to be custom developed: If 60 reusable components were planned with average component size as ' 100 LOC and software engineering cost for each LOC as $ 14, then the risk exposure would be

A. $ 25,200
B. $ 20,160
C. $ 17,640
D. $ 15,120
Answer» E.