Anil can complete a work in 15 days by working 8 hours per day. Sanjay can complete the same work in 25 days by working 6 hours per day. If both of them work together 9 hours each per day, In how many days the work will be completed? |
| A. | \(6\frac{{13}}{{27}}\) days |
| B. | \(6\frac{{11}}{{27}}\) days |
| C. | \(7\frac{{11}}{{27}}\) days |
| D. | \(7\frac{{13}}{{27}}\) days |
| Answer» D. \(7\frac{{13}}{{27}}\) days | |