| 1. |
An industrial consumer has a daily load pattern of 2000 kW, 0.8 lag for 12 Hrs and 1000 kW UPF for 12 Hrs. The load factor is _______ |
| A. | 0.04 |
| B. | 0.06 |
| C. | 0.6 |
| D. | 6.0 |
| Answer» D. 6.0 | |