1.

A workpiece of 2000 mm length and 300 mm width was machined by a planning operation with the feed set at 0.3 mm/stroke. If the machine tool executes 10 double strokes/min, the planning time for a single pass will be

A. 50 min
B. 100 min
C. 200 min
D. 220 min
Answer» C. 200 min