A work is done in 12 days by a team of 10 men, the same work is completed by a team of 10 women in 6 days. If both work together then in how many days the same work can be completed- |
| A. | 4 |
| B. | 6 |
| C. | 9 |
| D. | 18 |
| Answer» B. 6 | |