A team of 30 men is supposed to do a job in 36 days. After 30 days some more men are employed and work was finished 2 days earlier. Then how many more men were employed? |
| A. | 17 |
| B. | 15 |
| C. | 13 |
| D. | 19 |
| Answer» C. 13 | |