A takes 3 days and B 2 days. Both worked together and finished the work, and got Rs.150. What is the share of A ? |
| A. | Rs.90 |
| B. | Rs.60 |
| C. | Rs.80 |
| D. | Rs.50 |
| Answer» C. Rs.80 | |