A simple stand - alone software utility is to be developed in ’C’ programming by a team of software experts for a computer running Linux and the overall size of this software is estimated to be 20,000 lines of code. Considering (a, b) = (2.4, 1.05) as multiplicative and exponention factor for the basic COCOMO effort estimation equation and (c, d)=(2.5, 0.38) as multiplicative and exponention factor for the basic COCOMO development time estimation equation, approximately how long does the software project take to complete?

A. 10.52 months
B. 11.52 months
C. 12.52 months
D. 14.52 months
Answer» C. 12.52 months