| 1. |
A person P takes 4 hrs time to complete a job and Q takes 6 hrs to complete the same job if they work together how much time will they require to complete the job? |
| A. | 1.2 hrs |
| B. | 1.8 hrs |
| C. | 2.4 hrs |
| D. | 3.0 hrs |
| Answer» D. 3.0 hrs | |