MCQOPTIONS
Saved Bookmarks
| 1. |
A manager and the head of engineering discuss a change to a major work package. After the meeting, the manager contacts you and tells you to complete the paperwork to make the change. This is an example of: |
| A. | Management attention to scope management. |
| B. | Management planning. |
| C. | A project expediter position. |
| D. | A change control system. |
| Answer» D. A change control system. | |