A is twice as fast as B and B is thrice as fast as C. All these together, with the help of D. finish a piece of work in 2 days. D alone takes 12 days to complete the same work. B and C starts the work and leave after 2 days. The remaining work will be finished by A in: |
| A. | \(2\dfrac{1}{3}\) days |
| B. | 1 day |
| C. | \(2\dfrac{2}{3}\) days |
| D. | 2 days |
| Answer» D. 2 days | |