| 1. |
A is more efficient than B and they together can complete a work in 24 days. Had A done 50% of the work and then B, the remaining work, then the work would have been done in 50 days. B alone will complete 40% of the same work in: |
| A. | 16 days |
| B. | 24 days |
| C. | 21 days |
| D. | 20 days |
| Answer» C. 21 days | |