A is 40% more efficient than B and both together can complete a work in \(9{3\ \over 8}\) days. If A works for the first five days alone and the remaining work completed by B. Then find in how many days total work will be completed ? |
| A. | \(15{1\ \over 5}\) Days |
| B. | \(20{1\ \over 2}\) Days |
| C. | 20 Days |
| D. | 16 Days |
| E. | 18 Days |
| Answer» C. 20 Days | |