A is 30% more efficient than B. a can complete a work in 23 days. If A and B work together, how much time will it take to complete the same work? |
| A. | 10 Days |
| B. | 13 Days |
| C. | 12 Days |
| D. | 11 Days |
| Answer» C. 12 Days | |