A grader working at 75% efficiency is used in clearing ditches and levelling and reshaping roads. It requires 3 passes while running at a speed of 5 kmph. If the lane length is 1 km, the total time (in h) required to complete grading one lane will be |
| A. | 1.00 |
| B. | 0.75 |
| C. | 0.80 |
| D. | 0.25 |
| E. | 0.50 |
| Answer» F. | |