A generating station has a maximum demand of 50 MW, a load factor of 60%, a plant capacity factor of 45% and if the plant while running as per schedule, were fully loaded. The daily energy produced will be ________ MW |
| A. | 7.20 M W. |
| B. | 72.0 M W. |
| C. | 0.720 M W. |
| D. | 720 M W. |
| Answer» E. | |