| 1. |
A generating station has a maximum demand of 20 mW, load factor of 60%, a plant capacity factor of 50% and a plant use factor of 72%. What is the reserve capacity of the plant, if the plant, while running as per schedule, were fully loaded? |
| A. | 10 MW |
| B. | 15 MW |
| C. | 2 MW |
| D. | 5 MW |
| Answer» E. | |