MCQOPTIONS
Saved Bookmarks
| 1. |
A fill having volume of 150000 m3 is to be constructed at a void ratio of 0.8 the borrow pit solid has a void ratio of 1.4. The volume of soil required to be excavated from the borrow pit will be |
| A. | 150000 m3 |
| B. | 200000 m3 |
| C. | 250000 m3 |
| D. | 300000 m3 |
| Answer» C. 250000 m3 | |