A contractor undertakes to complete the construction of a tunnel 720 meters long in 240 days and employs 60 men for the purpose. After 120 days, he finds that only 240 meters of the tunnel is complete |
| A. | 70 men |
| B. | 60 men |
| C. | 55 men |
| D. | 80 men |
| Answer» C. 55 men | |