A contractor takes a contract to complete a road in 60 days and employed 105 labours. After 25 days, he found that one-third of the work is completed. How many more labours he required to complete the remaining work in time? |
| A. | 75 |
| B. | 105 |
| C. | 150 |
| D. | 45 |
| Answer» E. | |