A Contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realised that the work would ge |
| A. | 10 % |
| B. | 14 2/7 % |
| C. | 20 % |
| D. | Can't be determined |
| Answer» C. 20 % | |