MCQOPTIONS
Saved Bookmarks
| 1. |
A contract is to be completed in 56 days if 104 persons work, each working at 8 hours a day. After 30 days, 2/5 of the work is completed. How many additional persons should be deployed so that the work will be completed in the scheduled time,each persons now working 9 hours a day? |
| A. | 160 |
| B. | 150 |
| C. | 24 |
| D. | 56 |
| Answer» E. | |