A contract is to be complete in 46 days and 117 men were set to work, each working 8 hours a day. After 33 days, 47 47 of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day ? |
| A. | 80 |
| B. | 81 |
| C. | 82 |
| D. | 83 |
| Answer» B. 81 | |