A certain piece of work can be completed by 12 men in 9 days. After they have worked for six days, six more men joined them. How many days will it take to complete the remaining work? |
| A. | 4 |
| B. | 2 |
| C. | 1 |
| D. | 3 |
| Answer» C. 1 | |