| 1. |
A certain number of persons can finish a piece of work in 100 days. If there were 10 persons less, it would take 10 more days to finish the work. How many persons were there originally? |
| A. | 90 |
| B. | 100 |
| C. | 110 |
| D. | 120 |
| Answer» D. 120 | |