A certain number of men complete a piece of work in 60 days. If there were 8 men more, the work could be finished in 10 days less. How many men were originally there? |
| A. | 20 men |
| B. | 30 men |
| C. | 40 men |
| D. | 50 men |
| Answer» D. 50 men | |