MCQOPTIONS
Saved Bookmarks
| 1. |
A certain number of men can do a piece of work in 54 days. If there were 30 more men, it would take 18 days less to complete the work. The number of men, initially, is: |
| A. | 50 |
| B. | 54 |
| C. | 72 |
| D. | 60 |
| Answer» E. | |