| 1. |
A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in: |
| A. | days |
| B. | days |
| C. | 0 days |
| D. | $10\frac{1}{2}$$days |
| Answer» D. $10\frac{1}{2}$$days | |