A can finish 80% of a task in 12 days and B can finish 20% of the same task in 2 days. They started the task together, but B left after 2 days and A continued to work. In how many days was the entire task completed? |
| A. | 17.5 |
| B. | 10 |
| C. | 15 |
| D. | 12 |