A can do as much work in 4 days as B can do in 5, and B can do as much work in 6 days as C in 7. In what time will C do a piece of work which A can do in a week? |
| A. | \(10\frac{5}{{24}}\) days |
| B. | \(4\frac{4}{5}\) days |
| C. | \(6\frac{8}{{15}}\) days |
| D. | \(12\frac{6}{{19}}\) days |
| Answer» B. \(4\frac{4}{5}\) days | |