A can do a work in 12 days and B can do it in 18 days. They started working together, but A leaves 3 days before the work gets over. For how many days did the two work together? |
| A. | 6 |
| B. | 5 |
| C. | 7 |
| D. | 7.2 |
| Answer» B. 5 | |