| 1. |
A can do a piece of work in 20 days. He worked for 5 days and B finished the remaining work in 42 days. B alone can do the whole work in how many days? |
| A. | 56 |
| B. | 52 |
| C. | 46 |
| D. | 64 |
| E. | 48 |
| Answer» B. 52 | |