| 1. |
A can do a piece of work in 18 days, B in 20 days and C in 30 days. B and C started work together but had to leave after 4 days. In how many days can A complete the work? |
| A. | 12 |
| B. | 6 |
| C. | 16 |
| D. | 8 |
| Answer» B. 6 | |