A can do a piece of work in 12 days while B alone can do it in 15 days. With the help of C, they can finish it in 5 days. If they are paid Rs.960 for the whole work how much money A gets.

A. Rs. 480
B. Rs. 240
C. Rs. 320
D. Rs. 400
Answer» E.