MCQOPTIONS
Saved Bookmarks
| 1. |
A can do a piece of work in 12 days. He worked for 4 days and B finished the remaining work in 36 days. B alone can do the whole work in how many days? |
| A. | 63 |
| B. | 54 |
| C. | 48 |
| D. | 72 |
| Answer» C. 48 | |