MCQOPTIONS
Saved Bookmarks
| 1. |
A can do 1 / 5 of a job in 10 days, B can do 1 / 3 rd of the job in 25 days. In how many days can they do half of the job working together? |
| A. | 30 |
| B. | 45 |
| C. | 15 |
| D. | 20 |
| Answer» D. 20 | |