A can complete a task in 18 days while B can complete the same task in 12 days. Both of them finish the task together and get Rs. 900. What is the share of B? |
| A. | Rs. 530 |
| B. | Rs. 360 |
| C. | Rs. 540 |
| D. | Rs. 750 |
| Answer» D. Rs. 750 | |