A, B and C can do a work in 6 days, 8 days and 12 days respectively. In how many days can all three of them working together, complete the work? |
| A. | 2 2/3 days |
| B. | 4 2/3 days |
| C. | 1 2/3 days |
| D. | 2 1/3 days |
| Answer» B. 4 2/3 days | |