A, B and C can complete a work alone in 400, 600 and 900 days respectively. In how many days can the work be completed if it is started by A and he is assisted by B and C on every second and third day respectively? |
| A. | 292 |
| B. | 270 |
| C. | 240 |
| D. | 295 |
| Answer» B. 270 | |