1.

A and B undertake to do a piece of work for Rs.200. A can do it in 6 days and B in 8 days. With the help of C they finish it in 3 days. How much is paid to C?

A. Rs.25      
B. Rs.26
C. Rs.27 
D. Rs.28
Answer» B. Rs.26